WinForms › Project Management › TaskLinkType
TaskLinkType
enum.NET 6 / 8 / 10.NET Framework 4.8Binarymission.WinForms.Controls.ProjectManagement
How a link between two tasks constrains the second.
public enum TaskLinkType
Members at a glance
FinishToFinish | The successor finishes once the predecessor has finished. |
FinishToStart | The successor starts after the predecessor finishes. By far the most common. |
StartToFinish | The successor finishes once the predecessor has started. Rare, but some plans need it. |
StartToStart | The successor starts once the predecessor has started. |
Members
FinishToFinish
The successor finishes once the predecessor has finished.
FinishToStart
The successor starts after the predecessor finishes. By far the most common.
StartToFinish
The successor finishes once the predecessor has started. Rare, but some plans need it.
StartToStart
The successor starts once the predecessor has started.