HypernovaDesktop Components · docs
Binarymission
WPF › Project Management › GanttColumns

GanttColumns

enum.NET 6 / 8 / 10.NET Framework 4.8Binarymission.WPF.Controls.ProjectManagement

The columns of the Gantt chart's task list. The task's name is always shown.

public enum GanttColumns

Members at a glance

AllEvery column.
AssigneeWho is doing it.
DefaultThe usual set: outline number, name, start, finish, duration and predecessors.
DurationThe length in working days.
FinishThe last working day.
NameThe task's name. Always shown, whether or not this flag is set.
NoneOnly the name.
PredecessorsThe incoming links, as a planner types them: 2, 3SS+1.
ProgressPercentage complete.
StartThe first working day.
WbsThe outline number: 1, 1.2, 1.2.3.

Members

All

Every column.

Assignee

Who is doing it.

Default

The usual set: outline number, name, start, finish, duration and predecessors.

Duration

The length in working days.

Finish

The last working day.

Name

The task's name. Always shown, whether or not this flag is set.

None

Only the name.

Predecessors

The incoming links, as a planner types them: 2, 3SS+1.

Progress

Percentage complete.

Start

The first working day.

Wbs

The outline number: 1, 1.2, 1.2.3.