ScheduleProblemKind
What kind of problem the scheduler found in its input.
public enum ScheduleProblemKind
Members at a glance
ConstraintConflict | A task that must start on a date is also held later by its links; the date is kept. |
DuplicateLink | The same link appears twice; the second is left out. |
DuplicateTask | Two tasks share an id; the first is used. |
InvalidDate | A date could not be read. Only text read by the charts can be invalid; it is ignored. |
LinkCycle | A link would make tasks wait for each other in a loop; it is left out. |
LinkWithinSummary | A link joins a summary to one of its own subtasks; it is left out. |
ParentCycle | A task's parent chain leads back to itself; it is shown at the top level. |
SelfLink | A link joins a task to itself; it is left out. |
UnknownParent | A task names a parent that is not in the plan; it is shown at the top level. |
UnknownTask | A link names a task that is not in the plan; it is left out. |
UnsupportedSummaryLink | A link leads into a summary by its finish, or out of one by its start, which a summary's rolled-up dates cannot honour; it is left out. |
Members
ConstraintConflict
A task that must start on a date is also held later by its links; the date is kept.
DuplicateLink
The same link appears twice; the second is left out.
DuplicateTask
Two tasks share an id; the first is used.
InvalidDate
A date could not be read. Only text read by the charts can be invalid; it is ignored.
LinkCycle
A link would make tasks wait for each other in a loop; it is left out.
LinkWithinSummary
A link joins a summary to one of its own subtasks; it is left out.
ParentCycle
A task's parent chain leads back to itself; it is shown at the top level.
SelfLink
A link joins a task to itself; it is left out.
UnknownParent
A task names a parent that is not in the plan; it is shown at the top level.
UnknownTask
A link names a task that is not in the plan; it is left out.
UnsupportedSummaryLink
A link leads into a summary by its finish, or out of one by its start, which a summary's rolled-up dates cannot honour; it is left out.